Line 324: Line 324:
 ^ Task    ^ Proposed date ^ Effective date^  ^ Task    ^ Proposed date ^ Effective date^ 
 |Choose the project proposal| 2025-03-01    |2025-02-28| |Choose the project proposal| 2025-03-01    |2025-02-28|
-|System Diagrams & Structural Drafts| 2025-03-12    |2025-03-12 and final version at |+|System Diagrams & Structural Drafts| 2025-03-12    |2025-03-12 and final version at 2025-05-28 |
 |Project Backlog, Global Sprint Plan, Initial Sprint Plan and Release Gantt Chart| 2025-03-15    |2025-03-15| |Project Backlog, Global Sprint Plan, Initial Sprint Plan and Release Gantt Chart| 2025-03-15    |2025-03-15|
 |List of Components and Materials| 2025-03-19    |2025-03-19| |List of Components and Materials| 2025-03-19    |2025-03-19|
Line 330: Line 330:
 |Interim Report | 2025-04-06 |2025-04-06| |Interim Report | 2025-04-06 |2025-04-06|
 |Interim Presentation| 2025-04-10 |2025-04-10| |Interim Presentation| 2025-04-10 |2025-04-10|
-|3D model video| 2025-04-15 |2025-04-15 and the final version at |+|3D model video| 2025-04-15 |2025-04-15 and the final version at 2025-05-28 |
 |Final List of Materials| 2025-04-29 |2025-04-29| |Final List of Materials| 2025-04-29 |2025-04-29|
 |Refined Interim Report| 2025-05-02 |2025-05-02| |Refined Interim Report| 2025-05-02 |2025-05-02|
 |Packaging Solution| 2025-05-14 |2025-05-14| |Packaging Solution| 2025-05-14 |2025-05-14|
 |Functional Tests| 2025-05-28 |2025-05-28| |Functional Tests| 2025-05-28 |2025-05-28|
-|Final Report, Presentation, Video, Paper, Poster and Manual| 2025-06-15 || +|Final Report, Presentation, Video, Paper, Poster and Manual| 2025-06-15 |2025-06-15
-|Final Presentation| 2025-06-18 || +|Final Presentation| 2025-06-18 |2025-06-18
-|Refined Final Report| 2025-06-25 || +|Refined Final Report| 2025-06-25 |2025-06-22|
-|Prototype and User Manual| 2025-04-10 ||+
 </WRAP> </WRAP>
 </table> </table>
Line 725: Line 724:
 | O         | Functional Tests    | Done      |   | O         | Functional Tests    | Done      |  
 | P         | Final Report    | Done      |   | P         | Final Report    | Done      |  
-| Q         | Presentation    | Ongoing         +| Q         | Presentation    | Done         
-| R         | Video    | Ongoing      |  +| R         | Video    | Done      |  
 | S         | Paper    | Done      |   | S         | Paper    | Done      |  
 | T         | Poster    | Done      |   | T         | Poster    | Done      |  
 | U         | Manual    | Done      |   | U         | Manual    | Done      |  
-| V         | Upload    | To do      |  +| V         | Upload    | Done      |  
 | W         | Prototype    | Done      |   | W         | Prototype    | Done      |  
 | X         | Change the interim report    | Done       | | X         | Change the interim report    | Done       |
Line 792: Line 791:
 | 13        | P     | 4             | All      | All | | 13        | P     | 4             | All      | All |
 | 13        | Q     | 4             | All      | All | | 13        | Q     | 4             | All      | All |
 +| 14        | R     | 3             | Pierre      | Pierre |
 +| 14        | P     | 4             | All      | All |
 +| 14        | Q     | 4             | All      | All |
 +| 14        | V     | 4             | All      | All |
 </WRAP> </WRAP>
 </table> </table>
Line 849: Line 852:
 | 13        | P     | 4             | All      | All |Ongoing| | 13        | P     | 4             | All      | All |Ongoing|
 | 13        | Q     | 4             | All      | All |Ongoing| | 13        | Q     | 4             | All      | All |Ongoing|
 +| 14        | R     | 3             | Pierre      | Pierre |Done|
 +| 14        | P     | 4             | All      | All |Done|
 +| 14        | Q     | 4             | All      | All |Done|
 +| 14        | V     | 4             | All      | All |Done|
 </WRAP> </WRAP>
 </table> </table>
Line 1151: Line 1158:
 </WRAP> </WRAP>
 In this sprint, the planned work was developed during the sprint. However, the team added a task on day three related to load and stress simulations. All this information is present in image {{ref>figure-sprint-13}}. In this sprint, the planned work was developed during the sprint. However, the team added a task on day three related to load and stress simulations. All this information is present in image {{ref>figure-sprint-13}}.
 +
 +
 +<WRAP round box>
 +<table table-sprint-14>
 +<caption>Sprint 14 - 12/05 to 18/06(velocity planned: 1w 1d 1h 20m and real velocity: 1w 6h 20m)</caption>
 +<WRAP center>
 +^ Product Backlog Item    ^ Assignee          ^ Planned Effort [h]     ^ Status ^ 
 +|Minute and week report |Tomás|0.5|Done|
 +|Refined list of materials|Pierre|5|Done|
 +|Finish the video|Pierre|8|Done|
 +|Finish the presentation|All|6|Done|
 +|Explanation of power budget and electrical diagram|Pierre|16|Done|
 +|Chapter 4|Aaro|6|Done|
 +|Chapter 7|Pierre and Waad|8|Done|
 +</WRAP>
 +</table>
 +</WRAP>
 +
 +<WRAP>
 +<figure figure-sprint-14>
 +{{ :burndown_chart_-_sprint_14.png?600 |}}
 +<caption>Burndown chart - sprint 14 (available capacity: 10h per person Friday: 3h Monday: 3h Tuesday: 4h)</caption>
 +</figure>
 +</WRAP>
 +In this sprint, the planned work was developed during the sprint. All this information is present in image {{ref>figure-sprint-14}}.
 ==== - Sprint Evaluations ==== ==== - Sprint Evaluations ====
  
Line 1998: Line 2030:
 The middle steel profile also incorporated a technical opening, which allowed cables to safely and neatly pass through the floor to and from the table, benches, and roof components. The technical opening denies any mechanical damage to wiring while storing them out of weather conditions, while maintaining a clean and manageable energy distribution system throughout the structure. The middle steel profile also incorporated a technical opening, which allowed cables to safely and neatly pass through the floor to and from the table, benches, and roof components. The technical opening denies any mechanical damage to wiring while storing them out of weather conditions, while maintaining a clean and manageable energy distribution system throughout the structure.
 As for the sockets, usb-c ports, and control switches have been carefully positioned- especially on the side of the table- to allow for universal and ergonometric functionality including for wheelchair users.  As for the sockets, usb-c ports, and control switches have been carefully positioned- especially on the side of the table- to allow for universal and ergonometric functionality including for wheelchair users. 
 +
 +
 +**__Material selection__**
 +
 +The material selection for this workstation design was based on structural performance, durability, cost, and appearance. Each detail was selected for the functional and aesthetic requirements of an outdoor workstation. 
 +The foundation is a concrete base that has good stability and compressive strength. This ensures that the entire structure is well anchored in relation to the environment and can withstand environmental pressure like wind and uneven ground. The team then used wooden joists to construct wooden decking, which was chosen for its natural appearance and warm texture, with durable properties for a weathered and stable walking surface.
 +The table and benches- the seating surfaces are composed of **oak wood** for durability, exterior weather resistance, and appearance. The legs of each bench and the table are made of aluminium for its corrosion resistance and lightweight characteristics, which are required in the design of modular outdoor structures. One bench includes a back rest, which consists of oak wood slats supported by an aluminium frame on the top and bottom for rigidity and comfort.
 +
 +Another feature at the bottom of the structure is a custom **aluminium** footrest in a chargable, interesting, and atypical shape. The footrest contributes to user comfort, and adds to the overall appearance, by introducing a dynamic shape at the level of the ground.
 +The central structural column is made from **S355 structural steel**. While aluminium was initially considered for its lightness, S355 steel was ultimately chosen due to its superior strength and lower cost for structural applications.
 +
 +S355 steel provides the necessary load means for the central core to take the upper structures and the roof. The central structure has a cylindrical wooden form cover, the wooden form helps to provide warmth and softness visually, while also integrating the central core as part of the rest of the wood elements in the design.
 +The roof is also made from S355 steel to ensure it is able to safely support the loading of the photovoltaic system and retractable shade systems. The strength and stability of steel is important to manage wind load and the weight of the photovoltaic system.
 +
 +Lastly, at the nase of the central structure, a custom aluminium box is incorporated to hold electrical components like batteries, controllers, and other electronics. Aluminium is perfect for this purpose because of its properties such as corrosion resistance, machinability, and thermal properties, keeping sensitive components safe in an outdoor application.
 +
  
 **__Drawings__** **__Drawings__**
Line 2350: Line 2398:
  
 In the prototype, due to the decision to prepare it with lightweight materials and scaled, as well as due to lack of access to the mechanical components at the moment of assembling it, the prototype does not include automatic adjustments of the originally ergonomic benches and table.  In the prototype, due to the decision to prepare it with lightweight materials and scaled, as well as due to lack of access to the mechanical components at the moment of assembling it, the prototype does not include automatic adjustments of the originally ergonomic benches and table. 
-The initial idea to counter this obstable was to use the motor, but the scale of the prototype made it impossible to attach it to work efficiently. +The initial idea to counter this obstacle was to use the motor, but the scale of the prototype made it impossible to attach it to work efficiently. 
  
 Therefore, the prototype in the field of adjustability sets on the illustration of the core idea of how the product should work, although the adjustments still have to be done manually.  Therefore, the prototype in the field of adjustability sets on the illustration of the core idea of how the product should work, although the adjustments still have to be done manually. 
Line 2453: Line 2501:
  
 The hardware measurement tests were performed as specified in  [[report|1.6 Tests]] . The hardware tests measure the working functions of the physical hardware and the extent to which they align with the intended design objectives. The results of the tests are summarized below: The hardware measurement tests were performed as specified in  [[report|1.6 Tests]] . The hardware tests measure the working functions of the physical hardware and the extent to which they align with the intended design objectives. The results of the tests are summarized below:
 +
 +
 +<caption>Functional results</caption>
 +<WRAP center>
 +^ Use case ^ Result ^
 +| UC1 - Automatic Lighting | Pass |
 +| UC2 - Adjustable work surface height | Pass |
 +| UC3 - Wi-Fi communication | Pass |
 +| UC4 - Sustainable energy autonomy| Fail |
 +| UC5 - Manually operated awnings | Pass |
 +</WRAP>
 +
 +
 +
 +The adjustable work surface is manually operated on the prototype.
  
 Some mechanical functionalities weren't implemented due to reflectivity with material paramaters and limitations of scaling. The automatic adjustment of benches and table surfaces, the team first intended to use a motor, however the limit of the prototype in scaling and mechanism access made this impossible. Leading to use of manual operation instead to simulate the intended adjustment capabilities. The smart control system is based on the ESP32 microcontroller which incorporates an OLED screen and built-in Wi-Fi module, as well as communication to TSL2561 luminosity sensor and HTU21D for temperature and humidity sensing and reproduction. Some mechanical functionalities weren't implemented due to reflectivity with material paramaters and limitations of scaling. The automatic adjustment of benches and table surfaces, the team first intended to use a motor, however the limit of the prototype in scaling and mechanism access made this impossible. Leading to use of manual operation instead to simulate the intended adjustment capabilities. The smart control system is based on the ESP32 microcontroller which incorporates an OLED screen and built-in Wi-Fi module, as well as communication to TSL2561 luminosity sensor and HTU21D for temperature and humidity sensing and reproduction.
Line 2479: Line 2542:
 **//2. Performance Tests//** **//2. Performance Tests//**
  
-Though specific numerical data about load, run-time, throughput, etc., was not presented in this version of the project, the performance testing did confirm that the 2 sec refresh cycle of the control loop was consistent throughout the entire testing process. ***In later versions, we will present averaged results over 10 cycles,  with standard deviation data to support the consistency and performance of the software simulation under varying conditions.+Though specific numerical data about load, run-time, throughput, etc., was not presented in this version of the project, the performance testing did confirm that the 2 sec refresh cycle of the control loop was consistent throughout the entire testing process. In later versions, we will present averaged results over 10 cycles,  with standard deviation data to support the consistency and performance of the software simulation under varying conditions.
        
 **//3. Usability Tests//** **//3. Usability Tests//**
Line 2485: Line 2548:
 A formal usability review using the System Usability Scale (SUS) is planned for the next testing cycles (future evaluation). The current prototype supports basic user interactions (i.e., lighting feedback, visibility of data on OLED), and further evaluation is needed to examine the intuitiveness, usefulness, and accessibility — especially during full-scale deployment. A formal usability review using the System Usability Scale (SUS) is planned for the next testing cycles (future evaluation). The current prototype supports basic user interactions (i.e., lighting feedback, visibility of data on OLED), and further evaluation is needed to examine the intuitiveness, usefulness, and accessibility — especially during full-scale deployment.
 ==== - Summary ==== ==== - Summary ====
-//Provide here the conclusions of this chapter and make the bridge to the next chapter.//+ 
 +This chapter presented the overall development process of the Co-venient outdoor workstation, detailing its evolution from concept to practical implementation. Key activities undertaken in this process included defining design requirements, selecting material types and sources, structural and electrical design, packaging considerations, and creating a staged prototype that functioned. Specific consideration was given to incorporating sustainability, ergonomics, and user needs in every design decision. The smart control system, built using the ESP32 microcontroller platform was developed and examined to test responsive environmental sensing, automated lighting capability, and networking ability. Functional and software testing validated several of the anticipated use case scenarios, demonstrating both the feasibility and potential of the concept. The prototype served as a proof of concept that demonstrated how the final product would work in a real world application. The next chapter will provide a critical reflection on the project, including lessons learned and directions for future development.
  